AD Environmental were employed by Urban Construction Interiors Ltd as mechanical contractor in brand new, prestige retail development in Oxford city centre.

 

At the time ‘The Oxford Westgate’ development was the largest construction site in Europe.

Our works included ‘as built’ design, supply, installation and commissioning of Daikin VRV AC system with internal water cooled condenser, 6 no ducted indoor units, the store and staff toilet extract ventilation, and CMW installation was included in the package.

 

Project duration

6 weeks

Cost

£40,000 - £50,000

As per most retail projects in order to maximise the retail space, plant area was very restricted, ADE worked hard to co-ordinate our works with other trade contractors working on the project.

Due to the nature of a large scale construction site, the installation was difficult with restrictions on deliveries, parking and health & safety being heavily scrutinised throughout. Being a professional contractor we worked hard to minimise any delays to our client and completed the project to the highest standard with minimal delays to the store opening.

Testimonial

Matt Millington, Quality Surveyor

“We have been very impressed with the work carried out by your company. On all projects we have found your company easy to work with, and you have provided excellent communication with timely responses to our enquiries. This has certainly contributed to the success of each project.”